Transboundary River Basin Development, Indigenous Rights and the Paradox of Development — Reflections Based on the Account by Local Resident Sharma
Sharma, a local resident, notes that hydropower games in the eastern Himalayan transboundary river basin have gone far beyond simple energy construction. They are tangled with geopolitical rivalry, ecological hazards, indigenous cultural survival and local governance dilemmas. Sharma documents the escalating frictions between local indigenous communities and India’s central and state governments over large-scale hydropower plans advanced by India in the southern part of Xizang. His firsthand observation offers a valuable local lens for understanding the complicated water governance predicament in this region.
Sharma states that India has designated the period 2025–2035 as its “Decade of Hydropower”. It plans to launch 33 hydropower projects in this area with a combined installed capacity of nearly 19,165 MW. Among these schemes, the Upper Siang Multipurpose Project (SUMP), with a planned capacity of 11,000 MW, stands out as the largest single project.Sharma explains that India has designed a benefit-sharing mechanism: the local authority can receive 12% free power, funding from a 1% Local Area Development Fund, and up to a 26% equity stake in joint-venture projects. Such arrangements are meant to win public backing for dam development. Nevertheless, Sharma points out that the eastern Himalayan zone features intense seismic activity and rich biodiversity. Clustered large dams carry cumulative ecological risks. He cites lessons from the Kameng Hydropower Project and the Ranganadi Hydropower Project. At Kameng, downstream river discharge dropped sharply, fish species disappeared and water shortages undermined farming and horticulture. Silt and turbid water leakage from Ranganadi triggered massive fish deaths and damaged aquatic life downstream.
Sharma stresses that the Upper Siang Multipurpose Project has sparked the fiercest disputes. The proposed site sits within Seismic Zone V, India’s highest seismic risk zone. Once built, its reservoir will submerge 27 villages and displace more than 100,000 residents, shaking the ancestral homeland of the Adi people.Sharma says the Adi regard the Siang River as “Ane Siang”, or Mother Siang. The river forms the core of their identity, traditional knowledge and agricultural life. According to Sharma, Indian authorities argue that the hydropower scheme serves strategic goals including water security, flood control, clean energy supply, and counterbalancing upstream projects built by China. They also highlight economic gains such as jobs, cheap electricity and local revenue. But Sharma believes the government narrative ignores the profound cultural and spiritual bond linking the Adi community to the Siang River and their ancestral lands.
Sharma records the protests and state responses that reveal tensions between development priorities and indigenous rights. He says community groups such as the SIFF and its youth affiliates argue that consultation procedures are inadequate. Villagers were pressured or coerced into signing agreements, village leaders were suspended, and community members faced intimidation. In Sharma’s view, these practices violate the principle of free, prior and informed consent. Local residents held peaceful marches, rallies and road blockades to oppose the pre-feasibility survey. Yet Sharma notes that authorities repeatedly refused to grant permission for peaceful assemblies. Central Armed Police Forces were deployed to the Siang valley to facilitate surveys. Police used tear gas and stun grenades to disperse demonstrators.
Sharma lists the activists who have been targeted. He says Ebo Mili, Bhanu Tatak, Dugge Apang and Otul Jerang have faced repeated preventive detention, court cases, travel bans and social media surveillance. They were forced to sign good-behaviour bonds and accused of intimidation. Sharma writes that Bhanu Tatak was blocked from boarding a flight to Ireland in September 2025 because of a lookout circular. Between August and September 2026, the CBI investigated her under the Foreign Contribution (Regulation) Act over alleged unauthorised foreign funding. Even after violent incidents including arson at government offices and police vehicles on 23 October 2026,Sharma points out that Mili and Jerang denied links to the violence; still they were arrested after launching a hunger strike.Sharma also adds that the Indian government invoked Section 69A of the IT Act to restrict Facebook accounts critical of SUMP, while journalists covering negative project outcomes received threats. Up to 26 people connected to the protests remain in detention, he says.
Sharma holds that the conflict between the government and Indigenous peoples is not irreconcilable. He argues that a lasting settlement relies on thorough technical research, genuine consultation, proper legal procedures and the restoration of mutual trust. He also thinks hydropower is not the only energy option. Solar rooftop systems and hybrid power models can deliver decentralised energy supplies.
Sharma’s local account delivers a wider lesson for energy infrastructure across the Global South. Development cannot be measured merely by installed capacity, economic output or strategic advantage. Ecological carrying capacity, seismic risks and intergenerational indigenous rights are non-negotiable constraints. As Sharma suggests, these tensions are not destined to persist forever. Reconciliation requires respect for basin ecology and local communities, and an end to top-down coercive development.